Our Proven Process for Residential Construction

At Velvet Pines, successful residential construction requires meticulous planning, expert execution, and seamless coordination. Our proven process ensures each phase is handled with precision and care, delivering high-end, sustainable, and cost-effective solutions. Explore the stages of our construction process below to see how we bring your vision to life with unwavering commitment to excellence and reliability.
residential timeline1
process1 left
Pre Construction Phase
3 to 6 Months
Learn More
residential timeline2residential timeline3residential timeline4residential timeline5residential timeline6residential timeline7residential timeline8

Partner with Velvet Pines for Your Dream Home

Choose Velvet Pines for a home-building experience that prioritizes quality, transparency, and client satisfaction. Contact us today to start turning your dream home into a reality.
Get started

Our Proven Process for Residential Construction

At Velvet Pines, successful residential construction requires meticulous planning, expert execution, and seamless coordination. Our proven process ensures each phase is handled with precision and care, delivering high-end, sustainable, and cost-effective solutions. Explore the stages of our construction process below to see how we bring your vision to life with an unwavering commitment to excellence and reliability.
Site Preparation
1 to 2 weeks
Learn Moreresidential process1
residential process2
Foundation
2 to 4 weeks
Learn More
Framing
1 to 4 weeks
Learn Moreresidential framing
Mechanicals &
EMP Installation
2 to 5 weeks
Learn More
Finishes
2 to 5 weeks
Learn Moreresidential process5
residential process6
Trims
2 to 4 weeks
Learn More
Flooring
1 to 2 weeks
Learn Moreresidential process7
residential process8
Final Orientation
Learn More

Partner with Velvet Pines for Your Residential Project

Choose Velvet Pines for a residential-building experience that prioritizes quality, transparency, and client satisfaction. Contact us today to start turning your residential project into a reality.
Get started
X
Site Preparation
We secure necessary local building authority approvals and permits for the home plan and home site improvements.
The home’s position on the site is determined before clearing occurs, considering factors like terrain, drainage, utility easements, and municipal requirements. The site is then surveyed and marked with stakes to show the final positioning. Trees and obstructions are cleared, and the soil is prepared for construction. Please note that some trees may be removed to establish proper drainage, and Velvet Pines reserves the right to remove existing trees as necessary, subject to state and local laws.
Timeline: 1 to 2 weeks (or longer, depending on weather and soil conditions).
residential site preparation
X
Foundation
The foundation is a critical phase of construction. It supports your entire house and must meet or exceed national and local building codes. Velvet Pines uses post-tension foundations designed by licensed engineers, which are superior to monolithic foundations.
Professional craftsmen form the foundation, install reinforcing steel cables and underground plumbing, treat the soil against termites, and place a vapor barrier. Concrete is poured, and steel anchor bolts are embedded to complete the foundation. The foundation is then stressed, tested, and inspected.
Timeline: 2 to 4 weeks.
residential foundation
X
Framing
After the foundation is placed, the structure is ready for the framing process. The frame is the skeleton of your home. Velvet Pines can build your home out of many structural materials - that’s the benefit of using us. Some of the standards are
  • Sill plates being treated to prevent termites
  • Double insulated thermo break windows
  • Insulated exterior doors
  • Fireplaces are placed in the frame
All Velvet Pines homes include fire blocking and steel structural supports in key areas for your safety.
We use treated lumber in key areas to control moisture and termites and engineered Oriented Strand Board roof decking with steel hurricane clips for maximum strength and safety. Your entire house is wrapped and sealed with sill plate air infiltration sealant, which protects your home against moisture and weather and saves energy.
Timeline: 1 to 4 weeks.
residential framing
X
Mechanicals & EMP Installation
In this phase, the internal organs of your home are installed, including HVAC, plumbing, and electrical systems. Our highly trained mechanics install energy-saving insulation and pre-wire your home for various modern conveniences. As an EPA-approved Energy \Star home builder, we take special care in applying the insulation to your home during this phase.
You’ll be invited for a “frame walk,” or orientation, to verify that all your selected options are in place.
Timeline: 2 to 5 weeks.
residential mechanicals
X
Finishes
This is the midway point of the building process. Finishes include drywall, stucco, roofing, siding, bricks, concrete walls, and all major interior and exterior surfaces. You’ll be invited for another inspection as countertops, cabinets, doors, trim, paint, and other elements are installed.
Timeline: 2 to 5 weeks.
residential finishes
X
Trims
During this two-week phase, faucets, sinks, light switches, towel bars, doorknobs, and other small hardware are installed, bringing your design to life.
Timeline: 2 to 4 weeks.
residential trim
X
Flooring
Flooring is installed in the final week to protect carpets and hardwood from damage. Minor adjustments, touch-ups, and a thorough cleaning are done, preparing the house for the final orientation.
Timeline: 1 to 2 weeks.
residential flooring
X
Final Orientation
Congratulations!
After weeks of hard work, it’s time for the final walk-through. You inspect your new home with us, ready to sign the closing papers and receive your keys.
residential orientation